Site Master Plan

DESCRIPTION

This is a project of 37 2 and 3 bedroom properties available for private rental that will be a tremendous asset to the local community on the site of a former potteries site and other mixed industries.

Works will commence in April 2018, and will be fully complete within the 87 week build programme.

PROJECT DETAILS

Client : Your Housing Group

Contact: Carole Dowd

Start Date: April 2018

Build Programme: 87 weeks

COMMENT

“We are delighted to start works at Grange Street on a piece of brownfield land that has been vacant for some years. It’s our latest development with our valued partners at Your Housing Group who we have worked with on a number of successful projects.”

Andy Garnett, MCI Developments